Delnote Constructions at Pelican Point
September 2000 - Pelican Point Information
The Pelican Point Power Station is a $400 million dollar
project undertaken by National Power. National Power was established
in 1991 when the UK's State owned Central Electricity Power
Board was privatized. Employing more than 4500 staff, National
Power is one of Europe's top 100 companies.
In February 1999 National Power tendered for and won the
right to build Australia's most advanced power station. The
State Government nominated Pelican Point as the preferred
location because of the land availability, proximity to the
states main gas supply pipeline, availability of cooling water
and ease of connection to the existing transmission grid at
nearby Torrens Island.
Regardless of the lease of ETSA, South Australia needs a
new power station to meet the states increasing electricity
needs. The power stations design features include:
- 500MW capacity
- Two energy efficient gas turbines, each 165MW
- Two waste heat boilers
- One steam turbine, 170MW
- Direct Sea water cooling
The building of the power station will have created over
400 jobs in South Australia during its construction and will
maintain a permanent staff of 30 at the site once completed.
Over $3 million dollars each year will go into the local community
economy and the project increases the potential for further
economical development in the region.
Delnote Constructions at Pelican Point
At Pelican Point, Delnote Constructions has completed the
construction of the following
- Condenser pit footing
- Control / Elect building
- Cooling water offshore works
- Construction transformer footing
- Emergency diesel slab
- Electro-chlorination building
- Feed water area 1
- Feed water are 2
- Steam turbine foundation
- ST transformer enclosure bay
- Store / Workshop building
- Waste water retention basin
- Water treatment area
- Seal and pump pit
The picture above shows our employees continuing the wall
for the Waste Water Retention Basin. As you can see all of
the safety hand rails are in place, ensuring a safe working
environment.
The total subcontract was worth $2 million dollars. The majority
of the contract was labour including formwork, concrete placement,
concrete pumping and other materials.
|