Over the last few years Delnote Constructions has been working in the industrial and commercial fields of construction. Spending over two years at Roxby Downs working on the Olympic Dam Expansion Project and more recently working on the Pelican Point Power Station.

Amcor Bottle Plant

Amcor commenced construction of its new wine bottle facility at Gawler in South Australia. The Premier of South Australia, The Hon. John Olsen MP attended the ground breaking ceremony. Click here for more details.

McLaren Vale Winery

Delnote Constructions was contracted to begin work at the McLaren on the Lake - Serafino Winery located in McLaren Vale South Australia. Click here for more details.

Hindmarsh River Bridge

Delnote Constructions was awarded the concrete and formwork to the Hindmarsh Rivver Bridge which is close to Victor Harbor. The work consisted of forming up and pouring of the head walls, the piers, the concrete deck, the edge beams and the whale tail shaped cross heads. Click here for more details.

Pelican Point Project

In February 1999 National Power tendered for and won the right to build Australia's most advanced power station. The State Government nominated Pelican Point as the preferred location because of the land availability, proximity to the states main gas supply pipeline, availability of cooling water and ease of connection to the existing transmission grid at nearby Torrens Island.

Delnote Constructions won the contract for concrete placement at the power station. Click here for more details.

Roxby Downs Olympic Expansion Project

At Roxby Downs we worked with Western Mining both above and below ground to improve the facilities at the mine. Initially the contract was for a six month period, however it was extended to a two year contract and totaled to $6.7million dollars. Click here for more details.


32 meter Putzmeister pump at Pelican Point